Hi Friends
I want to post actual labour hours in C015. I dont see any field in C015 to enter actual labour hours manually.
When I use C015 for production order final confirmation, it takes planned hours from the routing master data and post as a actual hours. But I want to enter the actual labour hours in C015 before posting. Is there a way or any other transaction.
CO11N is the only way or is there any other options ?
Thanks/Regards
Vijayasankar. R